Case

2025-07

11

On-site No-Landing harmless treatment for waste drilling mud

  • Project location: Yulin, Shaanxi

  • Customer name: A certain company of Sinopec

  • Processing scale: Annual processing of 25 wellheads, approximately 38000 cubic meters of mud

  • Time: 2014-present

  • Solid phase resource utilization pathway: Solid phase meets the requirements of brick making and supplies local building materials factories

  • Liquid phase resource utilization pathway: After purification treatment, it can be reused or dust suppressed at the well site, with a comprehensive utilization rate of over 95%