Case

2025-07

11

On-site No-Landing harmless treatment for waste drilling mud

  • Project location: Fuling, Chongqing

  • Customer name: Zhongyuan Drilling Branch

  • Processing scale: Annual processing of 13 wells, approximately 19500 cubic meters of mud

  • Time: 2017-present

  • Solid phase resource utilization pathway: Solid phase reaches a moisture content of less than 30%, various heavy metals meet relevant parameter requirements, and is directly used for road paving

  • Liquid phase resource utilization pathway: After purification treatment, the well site is sprayed with water to suppress dust and reduce dust pollution